Lembah Sireh : Riverfront project down the drain : The Star
KOTA
BARU: A RM2bil development project on the riverfront here that was to
be ready in 2015 remains little more than a plan two years after the
Auditor-General alerted the state government of its shortcomings.
The
10km-long project is supposed to be completed on Aug 31, 2015 just two
years from now based on the exchange of letters between the developers Liziz Standaco Sdn Bhd (LSSB) and the State Economic Planning Unit.
The
project was touted to involve 2,400 shop-offices, a hotel, a
hypermarket, a golf course, luxury apartments and residential houses.
But only a hypermarket and some shoplots have been built since 2003 when
the 404.6ha project was first announced and some 130 farmers ordered to
move out.
Some RM389mil worth of infrastructure and other
supplementary projects and cash have yet to be delivered although the
agreement with LSSB is about to expire.
The
non-delivery of projects such as a mosque, roads, bridges and a
low-cost housing scheme has led to the Auditor-General asking questions
and the Malaysian Anti-Corruption Commission investigating.
The
Auditor-General's Report for 2011 stated that the contractor LSSB owed
the state government more than RM12mil as contribution towards a
low-cost housing scheme.
Sources said some of the transactions showed that LSSB had not met its obligations to the state.
“The
company owes the state RM389mil. While claiming that it did not make
enough money to fulfil its obligations, it paid out more than RM400mil
in the past five years to its directors,” said one source.
Last year, LSSB declared its biggest loss yet of RM7.1mil. What puzzled MACC was that the directors were still paid RM75.5mil.
The
agreement also required LSSB to build the Sultan Yahya Petra Bridge. It
didn't. The Federal Government took over the RM90mil project and the
company has not paid for it.
Four parcels of land were alienated
to LSSB under a 99-year leasehold. The land runs some 10km along both
sides of Sungai Kelantan covering areas such as Jambatan Sultan Yahya
Petra to Pulau Jerami, Kota Baru, Kampung Palekbang and Tumpat.
Under
the agreement signed on July 8, 2003, the company has until 2015 to
build the shop-offices, hotel, hypermarket, golf course, luxury
apartments and residential houses.
The
project includes the building of 600 units of high-end bungalows,
semi-detached and terrace houses, and public housing and facilities
besides commercial development.
In return for the land, LSSB is supposed to pay the state in cash and build infrastructure.
After
10 years, the state has not received any money nor has any of the
promised infrastructure been built, according to sources. The agreement
was originally for 12 years although it allows for extensions.
Another
point of interest for the MACC investigators is that the agreement also
allows LSSB to substitute “some other form of benefits in kind” as long
as the substituted benefit is “equal to the total sum set out”.
This
has led to a puzzling transaction where the developer has handed over a
4.8ha area, purportedly the site for a palace. The developer valued the
land at RM41mil.
“There is not even a single completed building
on the site. All they did was level the land. There was never a proposal
for a palace in the original agreement,” said an official familiar with
the contract.
MACC chief commissioner Datuk Seri Abu Kassim Mohamed confirmed that a team was looking at the papers on the project.
He said the investigators had been in touch with the state government and LSSB officials but declined to elaborate.
Meanwhile, LSSB officials declined to comment on the queries while the Deputy Mentri Besar Datuk Ahmad Yaakob could not be reached for comment.
At
the same time, small-time entrepreneurs and investors who banked
heavily on the project have seen their investments go up in smoke.
Many
of the traders have rented lots, hoping to cash in on the traffic that
would come with the Lembah Sireh project but have seen only a handful of
customers trickle in.
Ulasan
Catat Ulasan